Multiobjective Resource-Constrained Project Scheduling with a Time-Varying Number of Tasks
Table 1
Properties of tasks.
| Task ID | Duration | | | | |
| 1 | 18 | 4 | 0 | 0 | 0 | 2 | 13 | 10 | 0 | 0 | 0 | 3 | 16 | 0 | 0 | 0 | 3 | 4 | 23 | 3 | 0 | 0 | 0 | 5 | 18 | 0 | 0 | 0 | 8 | 6 | 15 | 4 | 0 | 0 | 0 | 7 | 19 | 0 | 1 | 0 | 0 | 8 | 12 | 6 | 0 | 0 | 0 | 9 | 17 | 0 | 0 | 0 | 1 | 10 | 19 | 0 | 5 | 0 | 0 | 11 | 22 | 0 | 7 | 0 | 0 | 12 | 16 | 4 | 0 | 0 | 0 | 13 | 23 | 0 | 8 | 0 | 0 | 14 | 19 | 3 | 0 | 0 | 0 | 15 | 10 | 0 | 0 | 0 | 5 | 16 | 16 | 0 | 0 | 0 | 8 | 17 | 15 | 0 | 0 | 0 | 7 | 18 | 23 | 0 | 1 | 0 | 0 | 19 | 17 | 0 | 10 | 0 | 0 | 20 | 22 | 0 | 0 | 0 | 6 | 21 | 27 | 2 | 0 | 0 | 0 | 22 | 22 | 3 | 0 | 0 | 0 | 23 | 13 | 0 | 9 | 0 | 0 | 24 | 13 | 4 | 0 | 0 | 0 | 25 | 17 | 0 | 0 | 4 | 0 | 26 | 18 | 0 | 0 | 0 | 7 | 27 | 23 | 0 | 8 | 0 | 0 | 28 | 17 | 0 | 7 | 0 | 0 | 29 | 20 | 0 | 7 | 0 | 0 | 30 | 20 | 0 | 0 | 2 | 0 | 31 | 12 | 6 | 0 | 0 | 0 | 32 | 17 | 0 | 0 | 0 | 1 | 33 | 19 | 0 | 5 | 0 | 0 | 34 | 16 | 0 | 0 | 0 | 8 | 35 | 15 | 0 | 0 | 0 | 7 | 36 | 23 | 0 | 0 | 0 | 0 | 37 | 18 | 0 | 0 | 0 | 7 | 38 | 23 | 0 | 8 | 0 | 0 | 39 | 17 | 0 | 7 | 0 | 0 | 40 | 20 | 0 | 7 | 0 | 0 |
|
|