Evaluation of Worker Radiation Exposure during the Kori Unit 1 Steam Generator Dismantling Process

Table 6

SG dismantling working time.

WorkMan-hour

Install of temporary auxiliary crane4
Installation of temporary lifting device of SG80
Install of rail and transportation cart24
Install protection plate12
Remove SG thermal insulation9
Transport SG thermal insulation8
Cut main steam pipe8
Cut main water supply pipe4
Cut others pipe9
Cut cold leg pipe9.5 (remote) + 13.5
Cut hot leg pipe10.5 (remote) + 13.5

SG: steam generator.