Logistical Simulation Modeling for Planning a Soil Remediation Process

Table 2

Soil input data for the model [2].

ParametersRaw DataInput Data
TypeValueTypeValue

Excavation Rate---30.0 tons/hr

Particle Size of SoilGravel (>4.75mm)6.3%Rubble (>60mm)1.0%
Gravel (60~4.75mm)5.3%
Sand(4.75~0.075mm)83.4%Sand (4.75~0.075mm)83.4%
Silt & Clay(<0.075mm)10.3%Silt (0.075~0.015mm)3.9%
Clay (<0.015mm)6.4%

Cleanup Process Rate---36.0 tons/hr