Feasibility Studies on Pyro-SFR Closed Fuel Cycle and Direct Disposal of Spent Nuclear Fuel in Line with the Latest National Policy and Strategy of Korea

Table 1

Dates of commercial operation and initial and to-be-extended design lifetimes for thirty-six units of Korean NPPs [27].

Number ReactorElectric power () Date of
Commercial operationEnd of initial design lifetimeEnd of extended design lifetime assumed

1Kori-15871978-04-292017-06-19No further extension
2Kori-26501983-07-252023-07-252043-07-25
3Kori-39501985-09-302025-09-302045-09-30
4Kori-49501986-04-292026-04-292046-04-29
5Shin Kori-110002011-02-282051-02-282071-02-28
6Shin Kori-210002012-07-202052-07-202072-07-20
7Shin Wolsong-110002012-07-312052-07-312072-07-31
8Shin Wolsong-210002015-07-242055-07-242075-07-24
9Hanul-19501988-09-102028-09-102048-09-10
10Hanul-29501989-09-302029-09-302049-09-30
11Hanul-310001998-08-112038-08-112058-08-11
12Hanul-410001999-12-032039-12-032059-12-03
13Hanul-510002004-12-312044-12-312064-12-31
14Hanul-610002005-04-222045-04-222065-04-22
15Hanbit-19501986-08-252026-08-252046-08-25
16Hanbit-29501987-06-102027-06-102047-06-10
17Hanbit-310001995-03-312035-03-312055-03-31
18Hanbit-410001996-01-012036-01-012056-01-01
19Hanbit-510002002-05-212042-05-212062-05-21
20Hanbit-610002002-12-242042-12-242062-12-24
21Wolsong-16791983-04-222022-01-012033-04-22
22Wolsong-27001997-07-012027-07-012047-07-01
23Wolsong-37001998-07-012028-07-012048-07-01
24Wolsong-47001999-10-012029-10-012049-10-01
25Shin Kori-314002016-04-012076-04-012096-04-01
26Shin Kori-414002017-02-012077-02-012097-02-01
27Shin Kori-514002021-03-012081-03-012101-03-01
28Shin Kori-614002022-03-012082-03-012102-03-01
29Shin Hanul-114002017-04-012077-04-012097-04-01
30Shin Hanul-214002018-02-012078-02-012098-02-01
31Shin Hanul-314002022-12-012082-12-012102-12-01
32Shin Hanul-414002023-12-012083-12-012103-12-01
33Cheonji-115002026-12-012086-12-012106-12-01
34Cheonji-215002027-12-012087-12-012107-12-01
35Shin Kori-715002028-12-012088-12-012108-12-01
36Shin Kori-815002029-12-012089-12-012109-12-01

: megawatt electric. Unit 1 is assumed to be shut down on June 19, 2017, permanently. continued operation of 10 years is assumed for Wolsong Unit 1.