Table 11

Cost of building biomass gasification plant.

Cost Potential

Capital costUp to 100 kW capacity~ 2000 USD/kW
Beyond 100kW capacity~ 1500 USD/kW

Maintenance costUp to 100 kW capacity~ 2.5 - 3 USD c/kWh
Beyond 100kW capacity~ 1.0 - 2 USD c/kWh

Operating costFuel cost~ 2.5 - 3 USD c/kWh

Power potentialBiomass consumption1.0 – 1.4 kg/kWh

Thermal energy potential1kg of fossil fuel replaced by 3.5 kg of biomass