Research Article
Operation and Economic Analysis for Ring Road: Baqubah City as Case Study
Table 4
Construction costs details.
| Segment | Part | Current condition | Upgrade | Length (km) | Cost $/km | Amount ($) |
| 1 | 1 | Excellent | Non | 10.5 | 0.0 | 0.0 |
| 2 | 1 | Excellent | Non | 2 | 0.0 | 0.0 | 2 | Very poor | Major | 8.5 | 900,000 | 7,650,000 |
| 3 | 1 | Good | Minor | 5 | 300,000 | 1,500,000 | 2 | Very poor | Major | 6.11 | 900,000 | 5,500,000 | 3 | Fair | Medium | 3.3 | 500,000 | 1,650,000 |
| Total | 16,317,000 |
|
|