Operation and Economic Analysis for Ring Road: Baqubah City as Case Study

Table 12

The second segment economic calculations.

YearAnnual volumeConstruction and maintenance costDiscount rate 5%Annual benefits ($)Discount rate 5%

003,825,0003,825,00000
103,825,0003,642,85700
55,974,66729,25022,9184,021,2433,150,749
106,926,27629,25017,9574,661,7232,861,894
158,029,45229,25014,0705,404,2152,599,520
209,308,33629,25011,0246,264,9662,361,200
229,875,21429,2509,9996,646,5032,272,106
7,825,01858,224,984