[Retracted] Multiobjective Optimization Management of Construction Engineering Based on Ant Colony Algorithm

Table 3

Summary of cost data of installation process of laminated plate components (yuan).

Serial numberProcess nameNormal modeRush modeSaving mode

1Mobilization and inspection of components15.516.513.9
2Erection equipment support22.423.520.7
3Cleaning of base course and construction surface5.26.14.3
4Layout of embedded parts12.514.710.4
5Hoisting and transportation of laminated plates36.4ā€”ā€”
6Installation of laminated plate in place17.018.2.15.8
7Grouting operation43.745.541.1
8Node protection8.49.07.2
9Site cleaning2.42.71.9