[Retracted] Multiobjective Optimization Management of Construction Engineering Based on Ant Colony Algorithm
Table 1
Summary of basic information of construction mode in installation process of laminated plate components.
| Serial number | Process name | Normal mode | Rush mode | Saving mode | Labor force (person) | Time (min) | Labor force (person) | Time (min) | Labor force (person) | Time (min) |
| 1 | Mobilization and inspection of components | 1 | 1 | 2 | 0.5 | 1 | 1 | 2 | Erection equipment support | 3 | 15 | 4 | 13 | 3 | 17 | 3 | Cleaning of base course and construction surface | 2 | 6 | 3 | 4 | 2 | 8 | 4 | Layout of embedded parts | 2 | 10 | 3 | 8.5 | 2 | 12 | 5 | Hoisting and transportation of laminated plates | 3 | 5 | — | — | — | — | 6 | Installation of laminated plate in place | 2 | 8 | 2 | 6 | 2 | 10 | 7 | Grouting operation | 2 | 15 | 3 | 12 | 2 | 17.5 | 8 | Node protection | 2 | 5 | 2 | 3 | 1 | 7.5 | 9 | Site cleaning | 2 | 3 | 0 | 2 | 2 | 4 |
|
|